Workshop Build
Work started on the 12th Jan 2018 to rebuild the ageing and partially destroyed warehouse.
Due to the devastating fire on march 1st 2017, the decision to build a new warehouse was now not a future project but an immediate requirement. To enable us to carry on working, we opted to build the new building over the old and once complete, remove the old building bit by bit from the inside. This is slow and expensive but it meant we didn’t have to relocate during the process.